@serenity Another update about the Maple upgrade:
- The blocking work from the Lilac upgrade is mostly done; there’s only one ticket left to complete next sprint.
- The conversation about remaining work from BB-4199 that is blocking the Maple upgrade is still ongoing, but shouldn’t keep us from getting started with initial planning for the upgrade epic.
So we can continue the process of finding an assignee for the Maple upgrade epic:
- @daniel and @gabor already had some clients and epics on their plates and recently took over additional ones, so they would likely end up spreading themselves too thin again by taking on the Maple upgrade.
- @adolfo will need to focus fully on LabXchange going forward, and won’t have capacity for any other epic/project going forward.
- @nizar is looking to take up the (non-cell) Developer Advocate role in the near future, so if he were to pick up the Maple upgrade now he’d likely have to pass it to someone else after while.
Based on these points it seems like our best options for taking ownership of the Maple upgrade would be @jvdm and @pooja. Would one of you be up for it?